When figuring the forward pass on a critical path, I start with zero. My colleagues say I should start with one, for the first day of the project. Each approach can give substantially different results, so which way is correct?

  1. The critical path is only used to get the start date on the project, so either way is correct.
  2. Start with zero to figure the critical path, as it is part of the set critical path formula.
  3. The critical path is recalculated every week, so alternate between the two methods.
  4. Look to see which task is the most valuable and select the start day of that task as the beginning of the critical path.

¿Cuál crees que es la respuesta correcta? Comprueba si has acertado en la web del Project Management Institute.

Tags:

0 comentarios

    Deja un comentario





    Trackbacks

    1. Bitacoras.com
    More in Gestión de proyectos (5 of 16 articles)


    Del 16 al 18 de noviembre de 2010, se celebrará en Barcelona el evento "Project Momentum 2010", organizado por Microsoft ...